Fairooz AlAwami | Lighting/Electrical
Dr. Richard Mistrick + Shawn Good
Boston Arts Academy
174 IPSWICH ST. Boston, MA 02215
Summary:
The building chosen for this thesis is the new Boston Arts Academy located in Boston, MA. The high school’s existing building is to be demolished and reconstructed on the same footprint. The new building will be an education/mixed use building, with a total square footage of 154,333 ft2 . This 5-story structure will include a variety of spaces such as academic classrooms, science classrooms, visual arts rooms, fitness rooms, filming/screening rooms, administrative offices, dining commons, and a kitchen. In addition, there will be large special spaces such as a gymnasium, auditorium, band recital hall, and an outdoor terrace on the fifth floor. This report encompasses the building’s year-long study. This process progressed from the understanding of the building’s existing conditions to the final development of architectural engineering designs. The report contains the following in detail:
o Lighting design solutions which were carefully developed to satisfy qualitative and quantitative design criteria. The four spaces which underwent lighting analysis and redesign are the building’s recital hall, outdoor terrace, main circulation space, and auditorium. The lighting design solution of the auditorium involved a change in the architecture. To insure the improvement in both aesthetics and function of the space an acoustical analysis was performed.
o Comprehensive study of the buildings electrical system including voltage drop and short circuit study. As well as, system design modifications such as transformer layout redesign and conduit material replacement.
o Cost comparisons between original and modified electrical system designs to prove that the design alterations are both reliable and cost effective.
The Boston Arts Academy encourages children to tap into their greatest artistic potential. Since this building is servicing the future of culture and change it is important to design for them to the best of our ability.
News Feed
Sent out personal and AE department "Thank You" notes
8/20/2018
Became career fair student host
8/25/2018
Resume submitted to AE career fair listing
8/27/2018
CPEP website posting
9/4/2018
Full functionality of CPEP website
9/10/2018
Uploaded Tech report 1B
9/24/2018
Updated building statistics
10/1/2018
Submitted tech report 2
10/22/2018
Submitted tech report 3
11/16/2018
Submitted final proposal
12/7/2018
Lutron presentation 12/3/2018
Added Abstract to website 10/26/2018
Added building statistics pt2 to website
10/17/2018
Submitted building abstract
9/29/2018
Added about me page
9/14/2018
Uploaded Tech report 1A
9/5/2018
Submitted building statistics part 1 draft
8/30/2018
Turned in initiation checklist 2
8/27/2018
Attended CPEP seminar
8/22/2018
Turned in initiation checklist 1 & confirmed master list information
8/20/2018
Obtained Owner Permission and CDs
7/25/2018
2018
2019
Finalist Thesis Presentation 4/26/2019
Final Thesis Presentation 4/11/2019
Final Report Submitted 4/1/2019
L/E Draft 2 Progress Submission 3/15/2019
L/E Draft 1 Progress Submission
2/16/2019
Final Thesis Proposal Revised
1/14/2019
Milestones Submission
2/14/2014
Milestones Submission
3/14/2014
Slide outline submission 3/27/2019
Final Presentation Submission
4/8/2018
Electrical trip to EATON 4/16/2019